Weijiao Power Plant Circulating Water Pump Station

After theReconstruction of the circulating water pump station project of Weijiao Power Plant, the electricity saving rate calculated according to the operating power is 20%. Due to the increased flow rate, the electricity saving rate calculated according to the energy consumption per ton of water can reach 30%.


潍焦电厂循环水泵站



Before pumping stationReconstruction

Water supply flow: 3150 M³/H

Outlet pressure: 0.19 MPA

Operating power: 257 KW

After pumping stationReconstruction

Water flow: 3600 M³/H

Outlet pressure: 0.22 MPA

Operating power: 205 KW